FOOTBRIDGE IN THE CLAUDE BERNARD DEVELOPMENT ZONE

Construction of a footbridge over the Paris Ring Road by the teams of Viry
A FOOTBRIDGE THAT FITS INTO ITS ENVIRONMENT
The footbridge is designed to prolong the pedestrian network to create a top quality urban connection. To the south, it comes as a continuation of Rue Lounes Matoub, extending the area of the concourse of the future cinema, and to the north it curves round to form a coherent pathway between the mass of the buildings and roads making up the future urban layout.

The structure, with a total length of 97.65 metres, consists of the main footbridge (with a span of 60 metres between the supports) with a central span and two anchor arms (stairs) and two side ramps.
97,6
metres long
200
tonnes of steel
A COMPLEX PROJECT
The particular features of the project lie in the double curve of the footbridge which also includes an asymmetrical camber, entailing a large number of parts that are all different.

The footbridge was erected during the night of 14 May 2015 with the help of two telescopic 700-ton cranes, with traffic being halted for a short period of just 6 hours.

The dimensions of the entire footbridge comply with the Eurocodes. It comes under the EXC4 category according to the EN 1090-2 standard.