4 HANGARS FOR THE A350
Castel & Fromaget constructed a building containing four Airbus A350 assembly units.
Designed by the Toulouse-based architects Calvo & Tran-Van, the structure is 35m high, 100m wide and 320m long. The work on this design and envelope construction contract (framework, roof, cladding, main doors) worth nearly €25m, managed by Castel & Fromaget, winner of the steel framework package, was done in 2013 after a 7- to 8-month design phase at Castel & Fromaget.
ADC equipped the building with 10 special bridge cranes: Eight 10-tonne triple-rail bridge cranes (length: 63.5m, height: 17m) and two 5-tonne two-rail bridge cranes (length: 22.5m, height: 26m). This final contract has a €3.25m budget.